Wednesday, May 30th

We have roughly 3/4 of the backside of the house in North Muskegon sided now. We also have all of the framing in place for the new back deck. The composite decking will be delivered on Friday and from there we will be installing that and the composite railing. Tomorrow we will start building a a covered porch over the front entry doors. Once we have that up we can install the new sidng on the front.