Friday, October 28, 2011

Friday

Wow! haven't had any new posts up lately but we've been busy. My computer has been in the shop due to a virus. In my last post I talked about the 24'x24' garage that we started in North Muskegon. We now have that one almost completed. We just have to finish up the siding and the garage door. We also just about finished the Norton Shores breezeway rebuild almost done too. The drywall was finished this morning and was primed and painted today. We'll install the new trim and that one will be wrapped up. After these two projects are complete, we will be starting a 24'x40' pole barn also in North Muskegon.

Wednesday, October 19, 2011

Wednesday

We formed up the foundation and concrete pour for the 24'x24' garage in North Muskegon today, in the rain! We did have to get some fill sand delivered, so tomorrow we will spread it out and compact it. Then we will need to get it inspected. From there we can pour once the weather cooperates.

Monday, October 17, 2011

Monday

We finished the shed addition in North Muskegon toaday. It turn out real nice and blended in with the existing shed perfectly! The Norton Shores remodel is going good too. The drywall is all hung now and the finishers will be in tomorrow to start finishing. From there it will need to be painted and trimmed out and that one will be done too. Tomorrow will be starting a 24'x24' garage in North Muskegon.

Thursday, October 13, 2011

Thursday

Its been a busy week! The shed addition in North Muskegon is just about finished. Its built and the siding is up. We just have to install the door and some trim and it will be wrapped up. The remodel in Norton shores is also coming along real well. All of the new framing is done, electrical is installed and drywall will be going up tomorrow.

Wednesday, October 5, 2011

Wednesday

Things are still going good on our Norton Shore Remodel project. We re framed a breezeway between the house and the garage and install 6 new windows. We also got some of the roof replacement done and that should be finished up tomorrow. From there we will install new electrical and drywall in the remodeled breezeway and that should do it for that one. The Shed in North Muskegon is just about all framed up as well. The roof shingles are going on tomorrow and from there its installing the new cedar siding, doors, and windows.

Tuesday, October 4, 2011

Tuesday

We made some good progress on both of our projects today. At the Norton Shores remodel we got a damaged section of roofing tore off and about halfway put back together. we also removed two walls and reframed them for some new windows. The windows will be installed tomorrow. In North Muskegon the 10'x14' shed concrete floor is poured and the shed is almost framed up. The cedar siding is being delivered tomorrow.

Monday, October 3, 2011

Monday

We started a new remodel/repair job in Norton Shores today as well as a 10'x14' shed addition in North Muskegon.