Thursday, March 29, 2012

Thursday, March 29th

We poured the concrete today for the 30'x40' pole barn in Fennville. It was a long day but we got it done. Tomorrow we will be installing the overhead garage doors and the service door. We will also be getting an inspection and then on to the interior on Monday.

Tuesday, March 27, 2012

Tuesday, March 27th

We got all of the prep work done today for the concrete at the pole barn in Fennville. We will be pouring Thursday morning. Tomorrow we will be staying in Muskegon and finishing up the interior of a garage at a house that we recently remodeled.

Monday, March 26, 2012

Monday, March 26th

The pole barn project down in Fennville is still coming right along. The whole building is now sided! We had to bring in 12 yards of fill sand to level the floor out for the new concrete floor. We spread all of that today and dug a trench for the new gas line as well. Tomorrow we will do the final grade and pour the concrete on Wednesday or Thursday. From there we just need to install the doors and then we will be ready to finish the interior.

Tuesday, March 20, 2012

Tuesday, March 20th

The 30x40' pole barn in Fennville is all framed up! We finished that portion of it today. Tomorrow morning the shingles are getting delivered and the roof will be installed by the end of the day. From there we will start the aluminum eaves, siding, and doors.

Monday, March 19, 2012

Monday, March 19th

The 30'x40' pole barn we are working on down in Fennville is going great so far. As of today we have all of the walls framed up and started installing the roof trusses today. We got about half of then installed today and will finish that up tomorrow morning. From there we will install the sheeting on the roof and walls. Shingles are coming Wednesday morning.

Thursday, March 15, 2012

Thursday, March 15th

We started the 30'x40' pole barn in Fennville today and it was a good start. This one is a building that burned down right before Christmas so there a concrete floor that we are working around. Today we cut some of the old concrete floor back to make room for the new poles. Tomorrow we will drill for the new posts and the inspector is coming to inspect the hole in the morning. From there we will begin the build.

Wednesday, March 14, 2012

Wednesday, March 14th

We tied up a few lose ends today. Tomorrow we are finally heading down to Fennville to re build a 30' x 40' pole barn that burned down last December. This one will be built to match the house and finished and insulated on the interior with a garage heater. A little travel involved for this one but we plan to put in some good hours and hopefully have it done in a couple weeks.

Tuesday, March 13, 2012

Tuesday, March 13th

We were back at the remodel in North Muskegon that we finished up last week. The owner decided to have us drywall the garage and repair some damaged concrete in the garage and the driveway. Today we finished the concrete repair and got the drywall first coated. We'll be back to second coat tomorrow morning.

Monday, March 12, 2012

Monday, March 12th

We finished up the remodel in North Muskegon last Friday! We had to go back and clean up a bit this morning. From there we went to another house in north Muskegon and installed some laminate flooring in a kitchen and dinning room. We finished that up today. Tomorrow we will be back at the house that we just remodeled to drywall the interior of the garage. We are trying to finish up some smaller projects. Later this week we are heading down to Fennville to build a 30'x40' pole barn.

Thursday, March 8, 2012

Thursday, March 8th

Had another good day at our remodel in North Muskegon. The new trim is all installed and everything we were initially going to paint is done. We did however get word from the homeowner that she would like the rest of the rooms painted and some new light fixtures installed. We made great progress today on the bathroom. The tub surround, new faucet and new vinyl floor are all in. We also got the walls freshened up in there too. We just have to reset the toilet and install the new vanity and that's done. Another good day tomorrow and we should wrap things up.

Wednesday, March 7, 2012

Wednesday, March 7th

We finished up the laminate flooring today at the remodel in North Muskegon. The wall board for the new tub surround was also installed and is all prepped for the shower walls to be installed tomorrow. We will also be installing new vinyl flooring in the bathroom tomorrow. We got a start on the trim today and should have that finished up tomorrow. If all goes well tomorrow and Friday, we should be done by the end of the week.

Tuesday, March 6, 2012

Tuesday, March 6th

We made some good progress on the remodel in North Muskegon today. We got all of the painting about done, we just have one more small section to finish up. We also got all of the old flooring ripped out and installed about half of the new laminate flooring. The bathroom is gutted and the new plumbing and tub were installed today. Tomorrow we will keep going on the floor and bathroom.

Monday, March 5, 2012

Monday, March 5th

We finished up everything over at Maranatha in Norton Shores last week. We installed some new siding on the third story of one of their apartment buildings. After the siding was up, we installed 12 awnings over the upper balconies. Today we started a remodel in North Muskegon. We are gutting a bathroom and completely redoing that, installing new laminate flooring in a bedroom, kitchen, and dining area, painting, and installing new trim.