Monday, February 28, 2011

Monday

The remodel project in Spring Lake is really starting to take its shape now! The electrical rough in is finally complete and we started hanging drywall today and should have it all hung tomorrow. The finishers will be coming in after that and it should be ready for paint by the end of the week. We will also start to prep for the tile in the mudroom/bathroom area later this week too. We will be starting on an outdoor smoking area at Northway Bowling Lanes while we are waiting for the drywall to get finished.

Thursday, February 24, 2011

Thursday

We made some good progress on the electrical at the Spring Lake project. The rough in portion should be finished tomorrow! We also started hanging the drywall for the new ceilings today. Tomorrow we should be able to get the rest of the ceiling done as well as some of the walls.

Wednesday, February 23, 2011

Wednesday

We grouted the tile in the Norton Shores bathroom, installed the new toilet, vanity and sink top. We also finished up the wiring for the garage in Fruitport. Now that all of these loose ends got tied up, we will be back in full swing on the Spring Lake Remodel. We should be hanging drywall there by mid day!

Tuesday, February 22, 2011

Tuesday

We're still making progress on the Spring Lake addition. There is a lot of new electrical getting retrofitted so its taking some time. We should be hanging drywall by this weeks end. We also relocated two window openings neccessary for the project. In the meantime, we went to Norton Shores and installed some tile in a bathroom and drywalled a wall. We'll be heading back tomorrow to grout and install the new cabinets and toilet.

Monday, February 21, 2011

Monday

The Spring Lake remodel is staying on track. The HVAC rough in was done today, the plumbing rough in is done, and the electrical rough in should be done tomorrow. From there we have to relocate two windows and then we're ready to hang drywall. Tomorrow we will be heading to Norton Shores to install some tile in a bathroom while we're waiting for the electrical.

Thursday, February 17, 2011

Thursday

The Spring Lake remodel project is progressing good! The demo is all done and the new framing is complete. We also had the plumbing and some of the electrical roughed in today. We should be hanging the drywall by the middle of next week. We are heading back to the garage in Fruitport to finish up the steel liner panels and blow in the insulation in the ceiling. The electrical was also started on that one taday too.

Tuesday, February 15, 2011

Tuesday

We got all of the framing finished up at the big Spring Lake remodeling project. We will be heading back tomorrow to demo the old kitchen and we will also be removing the old exterior wall which separates the old portion of the house and the new addition. We will also be finishing up the the steel in the garage in Fruitport.

Monday, February 14, 2011

Monday

We started the demo and some of the framing for the Spring Lake remodel project. We got a little further  than I originally thought we would, but thats a good thing. We should have the rest of the new framing done tomorrow and the rest of the demo done on Wednesday. From there the Plumber, Electrician, and the HVAC guys will come in on Thursday to rough in their portions.

Friday, February 11, 2011

Friday

We installed the liner steel on the ceiling today in the Fruitport garage. The rest of the steel should be in on Monday to complete the rest. Also on Monday we will be beginning an extensive remodel on a house in Spring Lake! This is some repeat business from a major addition project from last year. It is going to be a nice one.

Thursday, February 10, 2011

Thurday

We finished framing the 30'x32'x14' pole barn in Crockery Township today. From there we headed back to the garage in Fruitport to get preped for finishing the interior with liner steel.

Wednesday, February 9, 2011

Wednesday

The Holton Garage project is a wrap! We have some photos posted here and on Facebook. They should be posted on the website soon as well. From there we stopped in North Muskegon to clear off a roof that we will be replacing in the Spring. Then we headed out to Fruitport and started insulating the interior of a garage. We are installing steel liner panel and running the electrical. We'll be back there tomorrow.

Tuesday, February 8, 2011

Tuesday

We finally finished the Holton garage project today! We finished medding all the drywall, got the opener installed and got the electrical finished up. Tomorrow we will be heading back for a final cleanup and should have some photos posted. We'll be heading over to Norton Shores to finish the interior of another garage with liner steel and also finishing up the pole barn in Crockery.

Monday, February 7, 2011

Monday

We were back out in Holton today. We installed all of the drywall and got most of the mud up. This one should finally be completed tomorrow! There are just a few more details to address, this one turned out real nice.

Friday, February 4, 2011

Friday

We came close to finishing up the framing for the pole barn in Crockery Township. We just have a little more roof ducking to install and it will be done. Monday we should be finishing up the Hoton garage as well. Next week we will be finishing the interior of another garage in Fruitport and then an extensive remodel in Spring Lake.

Thursday, February 3, 2011

Thursday

We finally got the electrical inspected and approved for the garage in Holton. We ran the wire for the garage door opener and installed all of the insulation today. We are ready to hang and finish the drywall on Monday and that should finish this one up! As for tomorrow, we will be heading back to Crockery Township to set the trusses and install the roof sheeting to wrap up the framing for that one.

Tuesday, February 1, 2011

Tuesday

WE are still waiting for the electrical inspection approval so that we can proceed with the intertior of the Holton garage! Should be done tomorrow, weather pending I'm sure. We headed back over to Crockery Township this morning and got the headers in place for the pole barn project. It's now ready for the trusses and sheeting. Hopefully Thursday we can wrap that one up. We'll see what the big storm brings tonight!