Monday, March 26th

The pole barn project down in Fennville is still coming right along. The whole building is now sided! We had to bring in 12 yards of fill sand to level the floor out for the new concrete floor. We spread all of that today and dug a trench for the new gas line as well. Tomorrow we will do the final grade and pour the concrete on Wednesday or Thursday. From there we just need to install the doors and then we will be ready to finish the interior.