Wednesday, June 22, 2011

Wednesday

We found out that there was no insulation in the walls of the house we are adding onto in Norton shores so today we blew in insulation in the existing walls. We also just about finished the soffit and fascia on the eaves. The electrical rough in is done as well as the plumbing so we should be able to insulate and drywall the first of next week. Tomorrow we will start on the new siding.

Tuesday, June 21, 2011

Tuesday

We finished up the roof just in time for the heavy rains at the Norton Shore addition! The plumbing rough in was completed today and the electrical rough in is about 80 percent. We should have all of the inspections for the rough ins completed by the end of the week and then its on to the interior. In the meantime we will get the siding installed on the outside.

Monday, June 20, 2011

Monday

We got about 90 percent of the roof installed on the Norton Shores house we put the addition on. We will finish that portion up tomorrow and start on the siding. We also got the new windows installed last friday. The exterior is almost there and then its on to the inside. E. W. Anderson Plumbing started the plumbing rough in today and the electrical rough in will start tomorrow by K&L Electric.

Thursday, June 16, 2011

Thursday

With the dry weather, today was much more productive! We got the rest of the roof trusses up and the new roof system framed back into the old part of the house. The shingles are being delivered tomorrow morning so we will get going on replacing the roof. We also got a few of the new windows installed today and some more of the soffit up. We put a new storm door on the front door as well.

Wednesday, June 15, 2011

Wednesday

We got started installing the new aluminum soffit and fascia on the house we're putting the addition on in Norton Shores. We also got a start on installing the roof trusses for the addition portion. The rain put a little damper on the afternoon. Hopefully it clears up tomorrow and can can keep progressing.

Tuesday, June 14, 2011

Tuesday

The addition project in Norton Shores is progressing well! Today we installed all of the substrate for the new vinyl siding and prepped the eaves for the new soffit and facsia. We also finished up framing the last of the new walls. Tomorrow morning the trusses will be delivered and we will get going on installing them right away.

Monday, June 13, 2011

Monday

We finished up the foundation for the addtion in Norton Shores last week. Today we installed the new floor section and got about 90% of the new walls framed up. Tomorrow we will finish up the walls and sheeting. We will also start installing the new soffit while we are waiting for the roof trusses to get deleivered on Wednesday.