Monday, March 21, 2011

Monday

Worked on the outdoor smoking area at Northway Bowling Lanes today. We got the opening cut in the old block wall for the new door accessing the outdoor area installed. The owners also decided that they wanted to enclose the side a little more so we got that all framed up. Just waiting for the rest of the steel to come in and we can wrap this one up. I was also informed that the new kitchen cabinets for the Spring Lake remodel will be in this week. We will also be starting and large roof and kitchen remodel in Blue Lake township this week.

Thursday, March 17, 2011

Thursday

We have been up in Fremont for the past two days while we've been waiting for the the materials to show up to finish up the smoking room at Northway Lanes. In Fremont we tore down and installed new rafters on a 24' x 18' of a house that have some major leaking problems. We were able to tear it off, install the new rafter system and re roof it all in two days. We also installed new vented eaves to try to prevent future problems. If the weather holds out we wiil be installing the steel roofing at Northway Lanes tomorrow.

Tuesday, March 15, 2011

Tuesday

We were back at the remodel in Spring Lake this morning. We re installed the siding on the back of the house were we moved a window and changed the size of another. We also had to relocate a dryer vent. There is a custome tile showe  being installed in the new bathroom area, so we finished up all of the prep work for that. From there we went back to Northway Bowling Lanes to cut the door opening in the block wall for the new entrance to the smoking area. The door will be installed tomorrow morning.

Monday, March 14, 2011

Monday

The framing is complete for the smoking area at Northway Lanes. We are just waiting for the steel roofing to come in later this week and we can finish that one up. Tomorrow we will cut the hole for the new door to enter the smoking area. We also checked in on the remodel project in Spring Lake. The drywall is all finished and primed. The paint has started going on and the hradwood flooring started going in today as well. We installed a new window for the new kitchen area and removed all of the old flooring. Its starting to look like a house again!

Thursday, March 10, 2011

Thursday

We finished up the block half walls today for the smoking area at Northway Lanes today. We also got some prep work done for the roof system. Tomorrow we will be constructing the roof and from there its the steel roofing and its a wrap!

Wednesday, March 9, 2011

Wednesday

We got rained/snowed out at Northway Lanes today. We headed back up to Twin Lake today to install three new toilets, a faucet, and a utility tub. This was a foreclosure that was a mess and we are getting it back up and running. We will also be building a new deck there. If the weather cooperates, we will be finishing up the block back at the bowling ally tomorrow. The materials for the roof system are also being delivered tomorrow.

Tuesday, March 8, 2011

Tuesday

We installed about 90% of the block half walls for the outdoor smoking area at Northway Bowling Lanes. We have to finish up the last row and install the wall cap. We should be building the roof system for it on Thursday. From there we will be waiting for the steel roofing to come in and then we can finish up! We will also be back on the Spring Lake remodel by the end of the week to begin preping for the ceramic tile.