Wednesday, February 23, 2011

Wednesday

We grouted the tile in the Norton Shores bathroom, installed the new toilet, vanity and sink top. We also finished up the wiring for the garage in Fruitport. Now that all of these loose ends got tied up, we will be back in full swing on the Spring Lake Remodel. We should be hanging drywall there by mid day!

Tuesday, February 22, 2011

Tuesday

We're still making progress on the Spring Lake addition. There is a lot of new electrical getting retrofitted so its taking some time. We should be hanging drywall by this weeks end. We also relocated two window openings neccessary for the project. In the meantime, we went to Norton Shores and installed some tile in a bathroom and drywalled a wall. We'll be heading back tomorrow to grout and install the new cabinets and toilet.

Monday, February 21, 2011

Monday

The Spring Lake remodel is staying on track. The HVAC rough in was done today, the plumbing rough in is done, and the electrical rough in should be done tomorrow. From there we have to relocate two windows and then we're ready to hang drywall. Tomorrow we will be heading to Norton Shores to install some tile in a bathroom while we're waiting for the electrical.

Thursday, February 17, 2011

Thursday

The Spring Lake remodel project is progressing good! The demo is all done and the new framing is complete. We also had the plumbing and some of the electrical roughed in today. We should be hanging the drywall by the middle of next week. We are heading back to the garage in Fruitport to finish up the steel liner panels and blow in the insulation in the ceiling. The electrical was also started on that one taday too.

Tuesday, February 15, 2011

Tuesday

We got all of the framing finished up at the big Spring Lake remodeling project. We will be heading back tomorrow to demo the old kitchen and we will also be removing the old exterior wall which separates the old portion of the house and the new addition. We will also be finishing up the the steel in the garage in Fruitport.

Monday, February 14, 2011

Monday

We started the demo and some of the framing for the Spring Lake remodel project. We got a little further  than I originally thought we would, but thats a good thing. We should have the rest of the new framing done tomorrow and the rest of the demo done on Wednesday. From there the Plumber, Electrician, and the HVAC guys will come in on Thursday to rough in their portions.

Friday, February 11, 2011

Friday

We installed the liner steel on the ceiling today in the Fruitport garage. The rest of the steel should be in on Monday to complete the rest. Also on Monday we will be beginning an extensive remodel on a house in Spring Lake! This is some repeat business from a major addition project from last year. It is going to be a nice one.